Dual or convertible quotes are treated as Metered quotes not CIC quotes | Budget Estimate | Quotation Contact Customer within 2 working days | Quotation Accuracy Scheme* | ||
---|---|---|---|---|---|
Type of Quotation | Timescale working days | Failure Payment one off | Timescale working days | Failure Payment per working date late | Failure Payment one off |
Budget Estimate Less Than 1MVA | 10 | £80 | |||
Budget Estimate 1MVA or More | 20 | £80 | |||
Demand LV Single Service/Service Alteration | 5 | £20 | £395 | ||
Demand LV Small Project (1-4 premises) | 15 | £20 | £780 | ||
Demand LV Other | 25 | £80 | * Customer can challenge if quoted charges are outside the published range of charges – without an explanation from NGED. Challenge must be within 60 calendar days of quote or 10 calendar days of acceptance. | ||
Generation LV | 45 | £80 | |||
Demand HV | 35 | £165 | |||
Generation HV | 65 | £165 | |||
Demand EHV/132kV Generation EHV/132kV | 65 | £245 | |||
UNMETERED - A scheme of 100 or less street lights or street furniture - LV | 25 | £20 |
Make Contact to Schedule Dates | Commence Works | Complete Works | Energise Connection | ||
---|---|---|---|---|---|
The clock starts from receipt of payment at Plymouth Accounts Receivable | The Agreed Date may be changed by the customer or NGED. Notes must be kept on Crown of agreed dates with customer and any changes to dates | ||||
Type of Connection | Timescale working days | Failure Payment per working date late | |||
Demand LV Single Service / Service Alteration / Demand LV Small Project | 7 | £20 | £40 | ||
Demand LV Other | 7 | £80 | £30 | £165 | £165 |
Generation LV | 7 | £80 | £30 | £165 | £165 |
Demand HV or Generation HV | 10 | £165 | £30 | £245 | £245 |
Demand or Generation EHV/132kV | 15 | £245 | £30 | £330 | £330 |
UNMETERED - A scheme of 100 or less street lights or street furniture – LV | |||||
Unmetered Complete Works on New Site | £20 | ||||
Unmetered Complete Works on Adopted Highway (35 working days) | £20 |
Quotation – Contact Customer within 2 working days | Information & Design Submissions – Send written response to design submission & POC information | Final Works & Phased Energisation | ||||
Type of Connection | Timescale working days | Failure Payment per working date late | Timescale | Failure Payment per working date late | Timescale | Failure Payment per working date late |
---|---|---|---|---|---|---|
CIC Demand LV | 15 | £80 | Design submission decision within 10 working days of request for approval | £80 | Complete final works - 10 working days Phased energisation works - 5 working days or later date as requested | £165 |
CIC Generation LV | 30 | |||||
CIC Demand HV | 20 | £165 | Design submission decision within 10 working days of request for approval | £165 | Complete final works - 20 working days Phased energisation works – 10 working days or later date as requested | £245 |
CIC Generation HV | 50 | |||||
CIC Demand EHV | 50 | £245 | Provide EHV POC within 30 working days | £80 | Inform the customer of planned date proposed to complete final works within 20 working days of ICP request | £330 |
CIC Generation EHV CIC Demand/Generation 132kV | 65 | £165 | Design submission decision - within 20 working days | £245 |
Quotation – Contact Customer within 2 working days | Information & Design Submissions – Send written response to design submission & POC information | Final Works & Phased Energisation |
Type of Connection / Supply Fault | Timescale (cannot be extended, exemptions* must be used) | Failure Payment per working date late |
---|---|---|
UMC1 unmetered emergency Works to remove immediate danger to the public or property | Attend on site within 2 hours | £80 |
UMC2 High priority fault repair (traffic lights) | Complete repairs within 2 calendar days | £20 |
High priority fault repair (not traffic lights) | Complete repairs within 10 working days | £20 |
Multiple unit fault repair | Complete repairs within 20 working days | £20 |
Single unit fault repair | Complete repairs within 25 working days | £20 |
Guaranteed Standard failure payments must be made within 10 working days of the delivery of the standard. | Connections GSoPs are automatic payments and cannot be paid by ex gratia. | £75* (*One off payment) |