Connections pricing guide

Use these pricing tables to plan your project costs and timescales. All prices exclude VAT and are based on typical connection scenarios.

Plan your connection costs with confidence

Important: These are indicative prices only. Your actual costs may vary depending on your specific requirements and site conditions.

For an accurate quote tailored to your project, use our Budget Estimate Tool or submit an application.

Fixed price works

Standard connection services with set pricing

 

Connection typeTypical prices (excl. VAT)Typical lead time from receipt of payment
Install PME

£136.80 to make an existing PME terminal available

£184.33 to make a new PME terminal available (usually requires a cut-out change)

3-4 weeks

Install 1ph isolator

£222.303-4 weeks
Install 3ph isolator

£308.50

3-4 weeks

Domestic service alteration

Modifications to existing domestic electricity services

 

Connection typeTypical time to receive quotationTypical price (excl. VAT)Typical lead time from payment to connection
Domestic service alteration (based on an underground service alteration with NGED carrying out excavation and reinstatement)4 days£2,6006 weeks

New connections

New electricity connections for homes and businesses

 

Connection typeTypical time to receive quotation (working days)Typical price (excl. VAT)Typical lead-time from offer acceptance and payment to connection
1 domestic connection

4 days

£2,5008 weeks

Up to 4 domestic connections

8 days£7,0008 weeks
Over 4 domestic connections (based on 5 typical connections with service works only)

12 days

£15,00010 weeks
Typical small business connection (up to 69kVA)8 days£6,0008 weeks
Multiple small business connections (based on 2 typical connections with low voltage service works only)12 daysPrice on request/application8+ weeks
Typical large business connection (HV)30 daysPrice on request/application20+ weeks
Extra high voltage connection60 daysPrice on request/application2+ years
Unmetered new connections (excluding Local Authority & PFI)12 daysPrice on request/application8+ weeks