We are preparing and issuing Gate 2 Phase 1 Variation Offers in batches as we receive the information we need from the National Energy System Operator, NESO.
Each batch contains projects connected to particular Grid Supply Points, or GSPs. The schedule below shows:
These dates and batch groupings are our best current view and may change as NESO confirms further information.
Projects in the same batch may not all receive their offer on the same day. We will update this page when the schedule changes and contact customers directly when their individual offer is ready.
Please check your GSP again, even if you have viewed this page before. Some offer dates have changed and Batch 10 has been split into Batches 10 and 11. The cards below show the current position, revised offer timing and customer acceptance deadline for each batch.
Find the GSP your project will connect to in the batches below. Each card shows the batch's current position, the GSPs included, key offer dates and when the customer acceptance period ends.
The date we expect to receive, or received, an initial view of the Transmission Owner Construction Offer information for that batch.
The date we expect to receive, or received, the information needed from NESO to prepare the offers in that batch.
When offers were issued, or are expected to be issued, to customers in that batch.
The date by which customers in that batch need to accept their offer.
Dates and batch groupings are indicative and may change.
We share the latest Connections Reform updates and answer customer questions through our monthly customer webinars.