Gate 2 Phase 1 offer schedule

We are preparing and issuing Gate 2 Phase 1 Variation Offers in batches as we receive the information we need from the National Energy System Operator, NESO.

Each batch contains projects connected to particular Grid Supply Points, or GSPs. The schedule below shows:

  • the current position of each batch
  • the GSPs included in each batch
  • when we expect an early view of the Transmission Owner Construction Offer, or TOCO, information
  • when we expect the Application to Vary, or AtV, information from NESO
  • when offers have been or are expected to be issued
  • when the customer acceptance period ends

These dates and batch groupings are our best current view and may change as NESO confirms further information.

Projects in the same batch may not all receive their offer on the same day. We will update this page when the schedule changes and contact customers directly when their individual offer is ready.

The batch schedule has changed

Please check your GSP again, even if you have viewed this page before. Some offer dates have changed and Batch 10 has been split into Batches 10 and 11. The cards below show the current position, revised offer timing and customer acceptance deadline for each batch.

 

Find your batch and key dates

Find the GSP your project will connect to in the batches below. Each card shows the batch's current position, the GSPs included, key offer dates and when the customer acceptance period ends.

 

Batch 1

Current position Offer issued

GSPs in this batch

  • Swansea North
TOCO information received 8 June 2026
AtV information received from NESO 10 July 2026
Offer issued 7 August 2026
Customer acceptance period ended 28 September 2026

Batch 2

Current position Offer issued

GSPs in this batch

  • Exeter
TOCO information received 6 July 2026
AtV information received from NESO 15 and 17 July 2026
Offer issued 14 August 2026
Customer acceptance period ended 5 October 2026

Batch 3

Current position Not applicable

GSPs in this batch

  • No Grid Supply Points are currently assigned to this batch
Early sight of TOCO information Not applicable
Expected AtV information from NESO Not applicable
Expected offer issue Not applicable
Customer acceptance period Not applicable

Batch 4

Current position Offer issued

GSPs in this batch

  • Landulph
  • Port Ham
  • Taunton
  • Upper Boat 132kV and 33kV
TOCO information received 24 July 2026
AtV information received from NESO 28 July 2026
Offer issued 7 September 2026
Customer acceptance period ends 19 October 2026

Batch 5

Current position Offer issued

GSPs in this batch

  • Bridgwater
  • Grange
  • Sandford
TOCO information received 3 August 2026
AtV information received from NESO 4 August 2026
Offer issued 14 September 2026
Customer acceptance period ends 26 October 2026

Batch 6

Current position Offer issued

GSPs in this batch

  • Alverdiscott
  • Axminster
  • Chesterfield
  • Indian Queens
  • Lea Marston
  • Pembroke

Chesterfield: Offers will now be issued with Batch 7.

TOCO information received 3 August 2026
AtV information received from NESO 14 August 2026
Offer issued 21 September 2026
Customer acceptance period ends 2 November 2026

Batch 7

Current position Offer issued

GSPs in this batch

  • Cardiff East
  • Drakelow
  • Pyle
  • West Burton

Drakelow: Offers will now be issued with Batch 10.

TOCO information received 20 July 2026
AtV information received from NESO 26 August 2026
Offer issued 28 September 2026
Customer acceptance period ends 9 November 2026

Batch 8

Current position Offer issued

GSPs in this batch

  • East Claydon
  • Iron Acton
  • Staythorpe
  • Willington

Staythorpe and Willington: Offers will now be issued with Batch 10.

East Claydon: Offers will now be issued with Batch 11.

TOCO information received 27 July 2026
AtV information received from NESO 7 September 2026
Offer issued 9 October 2026
Customer acceptance period ends 16 November 2026

Batch 9

Current position Offers being prepared

GSPs in this batch

  • Berkswell
  • Coventry
  • Rassau
  • Uskmouth

Rassau: Offers will now be issued with Batch 8.

TOCO information received 3 August 2026
AtV information received from NESO 11 September 2026
Expected offer issue Week commencing 12 October 2026
Customer acceptance period ends 23 November 2026

Batch 10

Current position Awaiting information

GSPs in this batch

  • Rugeley
TOCO information received 10 August 2026
Expected AtV information from NESO 12 October 2026
Expected offer issue 20 November 2026
Customer acceptance period ends 28 December 2026

Batch 11

Current position Awaiting information

GSPs in this batch

  • Grendon
  • Cellarhead
  • Walpole
  • Ratcliffe
Expected TOCO information 16 October 2026
Expected AtV information from NESO 19 October 2026
Expected offer issue 27 November 2026
Customer acceptance period ends 4 January 2027

What the dates mean

Early sight of TOCO information

The date we expect to receive, or received, an initial view of the Transmission Owner Construction Offer information for that batch.

Application to Vary information from NESO

The date we expect to receive, or received, the information needed from NESO to prepare the offers in that batch.

Offer issue

When offers were issued, or are expected to be issued, to customers in that batch.

Customer acceptance period ends

The date by which customers in that batch need to accept their offer.

Dates and batch groupings are indicative and may change.

Find out more