We are preparing Gate 2 Phase 1 Variation Offers in batches as we receive the information we need from the National Energy System Operator, NESO.
Each batch contains projects connected to particular Grid Supply Points, or GSPs. The schedule below shows:
These dates and batch groupings are our best current view and may change as NESO confirms further information.
Projects in the same batch may not all receive their offer on the same day. We will update this page when the schedule changes and contact customers directly when their individual offer is ready.
Please check your GSP again, even if you have viewed this page before. The cards below show the latest batch positions and expected offer dates.
Find the GSP your project will connect to in the batches below. Each card shows the batch's current position, the GSPs included and the latest expected dates.
The date we currently expect an initial view of the Transmission Owner Construction Offer information for that batch.
The date we currently expect NESO to send the information needed for us to prepare the offers in that batch. For batches where this has already been received, the card may show the confirmed receipt date instead.
The week we currently expect to send offers to customers in that batch.
Dates and batch groupings are indicative and may change.
We share the latest Connections Reform updates and answer customer questions through our monthly customer webinars.