If you need to disconnect your electricity supply there are two options available;
You can arrange for the supply to be de-energised and re-energised by calling your Electricity Supplier.
The Electricity Suppliers name, address and telephone number will be shown on your electricity bill or use our Who is my Supplier tool
Contact us directly by either completing our online general enquiries form or call us on 0800 0963080.
We will require the following information to allow us to proceed with a disconnection request;
We will make a charge for carrying out disconnection work. The charges are individually assessed for each request and will vary dependent on the works involved.
Normally low voltage service termination equipment will be removed within 21 working days but up to six months' notice may be required to remove high voltage substation plant. In the case of EHV connections we should be consulted at an early stage and a programme for the removal of equipment agreed.
We will inform your supplier of the planned disconnection works, however you will need to contact them directly to terminate your supply contract(s).
Find out more by viewing this document about disconnections associated with cannabis cultivation.