These processes may be followed where you are installing generation and energy storage installations that are either rated above 16A (3.68kW) per phase or that do not meet the requirements of the current version the Energy Networks Association (ENA) Engineering Recommendation G98.
Where G99 applies, installations must comply with the ENA document ER G99 “Requirements for the connection of generation equipment in parallel with public distribution networks”
Smaller installations have a simplified process of application
Follow this process if you wish to make an application.
We would advise that you contact the generation manufacturer directly to enquire about the rating of the equipment.
Some types of generation (e.g. PV Solar) produce Direct Current (DC) electricity. Where this is the case they have to be connected to our network through inverters which convert the electricity to Alternating Current (AC) before it is connected to our network. The rating of this type of generation is deemed to be the inverter’s continuous steady state rating.
For example, a single phase PV solar installation that uses a 4kW inverter is deemed to have a rating of 4,000 ÷ 230 = 17.39A, which is just over the 16A per phase threshold, assuming the generation operates at a power factor of 1.0 (i.e. unity power factor).
We have a number of connection offer types we can provide, including a Study & Offer approach which enables you to request that we consider the design solutions for up to 3 different capacities, alternative connections for areas affected by network constraints and traditional connection offers to provide the full requested capacity.
More information is available in the website section Types of Connection Offer Available.
Fast Track SGI 1 | Fast Track SGI 2 | Fast Track SGI 3 | Less than 50kW | Greater than 50kW & less than 1MW (Type A) | 1MW to less than 10MW (Type B) | 10MW to <50MW (Type C) | Greater than or equal to 50MW or > 110kV (Type D) | |
---|---|---|---|---|---|---|---|---|
Applicable Standard | G99 | G99 | G99 | G99 | G99 | G99 | G99 | G99 |
Application | Not Required | Form A1-2 | Form A1-2 | Form A1-1 | Standard Application Form | Standard Application Form | Standard Application Form | Standard Application Form |
Notification | Form A3-3 | Form A3-2 | Form A3-2 | Form A3-1 | Form A3-1 | |||
Evidence | Must be Type Tested | Must be Type Tested | Must be Type Tested | If not type tested- Form A2-1 Synchronous <50kW Or Form A2-3 Inverter connected gen | If not type tested - Form A2-2 Synchronous & Form A2-3 Inverter connected gen | PGMD Form B2-1 | PGMD Form C2-1 | PGMD Form C2-1 |
Compliance & Commissioning Checks | Form A2-4 if the interface protection is not type tested or for other site compliance tests | Form B2-2 if the interface protection is not type tested or for other site compliance tests | Form C2-2 if the interface protection is not type tested or for other site compliance tests | Form C2-2 if the interface protection is not type tested or for other site compliance tests | ||||
Installation | Form B3 | Form C3 | Form C3 | |||||
EON, ION, FON | FON Types B-D: FON obtained during compliance testing & commissioning phase | FON Types B-D: FON obtained during compliance testing & commissioning phase | ION, EON, FON For Type D only: ION & EON obtained during Energisation Planning phase |
All application forms can be found on the ENA website here.
Please complete the G99 standard application form. As a minimum, parts 1-3 should be completed at application stage. Parts 4 and 5 shall be completed where the information is available and, in any case, should be submitted prior to the connection being made.
Where the power generating module is fully type tested and registered in the ENA Type Test Verification Report Register, application form A1-1 should be completed.
Where the power generating module is not type tested or only part type tested, application form A1-1 should be completed and submitted along with one of the following forms (as appropriate):
For G99 Fast Track processes please click here.
Engineering Recommendation G99 sets out the requirements for commissioning tests and checks. It is the responsibility of the installer to undertake these tests and ensure the generation units meet all the relevant requirements.
In some instances, we may need to witness the testing which will incur a fee. For further information regarding our fees please click here. We will notify you in advance should a witness test be required.
The following guidance documents contain further information relating to the:
EHV/132kV guidance document
HV/LV guidance document
G99 Connection Procedures Guidance Document
We use essential cookies to make our website work and provide you with a good experience. Full details can be found in our cookie policy . We'd like to set additional cookies to understand how you use our website and remember your settings.