You can apply online to connect 5 or more domestic properties using our Connections Online Application Form. Click the button below to begin.
You can also download an application form here.
You can download our guidance document here.
You will need:
It’s easy to find out if we work in your area, all we need is your site postcode.
By creating new connections to our power network, or modifying existing connections, we can provide access to the power you need.
Find out more about our connections process and what you need to apply.
Once we have your application, we will send you a connections offer. This will be valid for 90 days and work will usually be carried out within this time frame.
The steps associated with connecting 5 or more dometic properties are set out below.
Your connections offer will take into account the cost of the connection you have requested. This will include:
needed from our existing network to your meter position
you can carry out the digging work on your own land if you wish, but we will excavate on any public highways. Take a look at our information on how to dig safely.
this includes local authority fees associated with digging on public highways .
we can supply your meter cabinet, but your builder will have to install it before works can begin
your Electricity Supplier will charge you for installing a new meter
internal wiring must be carried out by a qualified electrician
if you have chosen to carry this out yourself
you will need to arrange for a builder to install your meter cabinet
We are here to answer your questions.
0800 0963080
Call us: Monday to Friday, 8am - 5pm
Alternatively, fill in a queries form and we will call you back the following day.
We’ve gathered important legal information here to help you find what you need.
Find out more about the types of offers and agreements available here.
Find out about Electricity Connection Offer Expenses Regulations