You will need:
It’s easy to find out if we work in your area, all we need is your site postcode.
Guidance procedures for the standard G99 Application Form. The connection guide for the distributed generation you are planning to install.
Application for connection of power generating modules with total aggregate capacity <50kW 3 phase or 17kW single phase.
Generating unit data. To be completed for all Type A, Type B, Type C and Type D Power Generating Modules.
This form should be used by all applicants considering installing an ELS as part of their connection application. This form should accompany the application for a connection.
Commissioning test requirements for ELS with an installed generation capacity exceeding 3.68kW, in addition to generation tests required by ENA EREC G83, G98, G59 or G99.
The DCODE (The Distribution Code of Licenced Distribution Network Operators of Great Britain) website hosts DG Connection Guides available for download.
Notes on Part 4 of the application
Should the information required in Part 4 not be available at the time of submitting your application, these may be submitted separately using the individual documents below.
Synchronous power Generating Modules. For Type A - Type D Power Generating Modules, Electricity Storage and transformers.
Power Park Module model data: doubly fed induction generating units. For Type A - Type D Power Generating Modules, Electricty Storage and transformers.
Power Park Module model data: electricity storage plan. For Type A - Type D Power Generating Modules, Electricity Storage and transformers.
Transformer information. For Type A - Type D Power Generating Modules, Electricity Storage and transformers.
We are here to answer your questions.
0800 0963080
Call us: Monday to Friday, 8am - 5pm
Alternatively, fill in a queries form and we will call you back the following day.
We’ve gathered important legal information here to help you find what you need.
Find out more about the types of offers and agreements available here.
Find out about Assessment and Design fees.