Disconnecting joint on existing HV mains – Non-contestable, to be carried out by NGED
Dismantling/removing existing overhead line – non-contestable, to be carried out by NGED
Dismantling/removing existing pole mounted transformer – Non-contestable, to be carried out by NGED
Disconnecting joint on the existing low voltage main to disconnect supply to existing building – Contestable, can be carried out by an ICP
Removal of supply at the existing building following disconnection – Contestable, can be carried out by an ICP
Design of upstream reinforcement required on the high voltage network – Non-contestable, to be carried out by NGED
Physical completion of upstream reinforcement works on the high voltage network – Non-contestable, to be carried out by NGED– except in instances where the reinforcement is sole funded
Determination of the Point of Connection – Trial – some ICP’s are able to carry out this element of the works Physical connection of the high voltage point of connection – Trial – some ICP’s are able to carry out this element of the works
Installation of new high voltage mains – Contestable – can be carried out by an ICP
Provision and installation of new substation – Contestable – can be carried out by an ICP
Provision and installation of new low voltage network to be used for services to new dwellings/units – Constestable – can be carried out by an ICP
Provision and installation of new services to individual dwellings/units – Contestable – can be carried out by an ICP
Diversion of cables for new site entrance (to lower the cables to achieve minimum depth)
Excavation & installation of cable – contestable
LV jointing – Non-contestable
HV jointing – Non-contestable
Disconnection & removal of existing cable – Non-contestable
Cookies Policy
We use essential cookies to make our website work and provide you with a good experience. Full details can be found in our
cookie policy
. We'd like to set additional cookies to understand how you use our website and remember your settings.