Stakeholders have asked us to provide an average cost of connection for high volume, low voltage on-street projects to support their planning and bidding for associated contracts, particularly under LEVI. CPOs and LAs are to note that the costs set out at 5.1 and 5.2 are indicative only as costs vary significantly according to the types of connection required in the programme, the region and the specific location. This means the average cost within a certain programme of connections, will vary depending on local circumstances of that programme. Costs may also increase over time, with significant increases in costs in the energy sector and related services in recent years.
We provide indicative costs both of a “typical connection” based on latest published costs and an average cost of connection based on historical connections and the associated dataset. Each example is confined to certain circumstances. National Grid Electricity Distribution cannot accept liability for any loss caused by acting in reliance on these examples.
When reviewing the average and typical costs, stakeholders should consider the following key variables which in general most significantly affect connection costs:
Length of the service and surface type
Type and size of existing cable
Local Authority Permit Charge
Excavation and Reinstatement of Cable Trench, and Lay of Cable Duct
Design Fees
Reconfiguration
In the sample data, seven out of 50 applications required reconfiguration. Of these seven, five were phase 8 applications and their average cost per connection was £7416, which is 60% higher than the overall average cost of phase 8 connections at £4662.
An example of network reconfiguration is given in the Connection Charging Statements, at example 20.
Licence area and locality within this
The costs of local contractors and services varies. This is why the Connection Charging Statements are produced by licence area, and ranges are provided within these for the same service. Costs in the South West tend to be higher than other licence areas.
These three averages are based on historic data for connections that were delivered in two different areas. Firstly in Coventry City under the On street Residential Charging Scheme (ORCS), and secondly from South Wales. The Coventry City data set includes 408 connections within 50 applications, connecting almost 1700 7kW charge points. These connections were a mixture of single phase and three phase, and grouped with 2 – 16 connections under each application according to localised geographical zones. All charge points were deployed in the context of terraced housing in an urban setting. The data set from South Wales includes 101 connections under 101 applications, in a mixture of urban, suburban and rural contexts, and a range of chargers from 7-50kW.
The notable difference between the South Wales and Coventry City costs, is largely due to longer service cables (i.e. distance from charge point to existing network) required in the more rural contexts of Wales. The lack of batching of the more geographically dispersed sites in South Wales is also a factor.
Notes on this data and average costs
1. Coventry City: Urban, batched connections inclusive of excavation - average cost £4,662 exclusive of VAT.
This was taken from phase 8 of the Coventry City On-street Residential Charge Point Scheme (ORCS programme. This data set included 26 applications, 186 connections and connected 849 charge points.
These quotes included the following items:
a) Assessment and design fees
b) Single or three phase underground service with a maximum kW / connection of 69kVA
a. Joint Supply and Installation including dig
b. Joint Hole
c. Cut-Out Supply and Installation
d. Other proportionally low-cost miscellaneous items e.g. alkathene tube, plastic marker tape, etc.
c) Installation of the cable in the foot path including excavation of joint and cable hole, and lay of ducting and cable.
The following costs were excluded:
d) The road closure permits were obtained by the Local Authority.
2. Coventry City: Urban, batched connections exclusive of excavation – average cost £1,506 exclusive of VAT.
This was taken from phases 3-7 of the Coventry ORCs project and included 24 applications, 222 connections and 828 Charge Points.
These quotes included the following items:
a) Assessment and design fees
b) Single or three phase underground service with a maximum kW / connection of 69kVA
a. Joint Supply and Installation (but not the dig of the hole)
b. Cut-Out Supply and Installation
c. Other proportionally low-cost miscellaneous items e.g. alkathene tube, plastic marker tape, etc.
The following costs were excluded:
The road closure permits were obtained by the Local Authority.
Excavation of the joint hole and cable channel, and lay of the ducting for the cable.
3. South Wales: Mixture of Urban and rural contexts, inclusive of the excavation, single connection per application (not bathced) - average cost £8,845
These applications were spread over a wide area and were not batched. The tendency in this data set to require longer service cables drive higher costs compared to Coventry.
These quotes included the following items:
a) Assessment and design fees
b) Single or three phase underground service with a maximum kW/connection of 69kVA
a. Joint Supply and Installation including dig
b. Joint Hole
c. Cut-Out Supply and Installation
d. Other proportionally low-cost miscellaneous items e.g. alkathene tube, plastic marker tape etc.
c) Installation of the cable in the footpath including excavation of joint and cable hole, and lay of ducting and cable.
This example cost is based on existing published information on connection costs set out in our Connection Charging Statements and Methodology for each of our 4 licence areas: East Midlands, West Midlands, South West and South Wales.
Section 7C explains the Assessment and Design fees
Section 7F describes the cost of a typical single/three phase underground service based on ground type, as well as a cost per metre for the cable installation (a usual service is between 2 and 8 metres).
We have provided further break down of a 'typical' cost of connection, so stakeholders could build other potential costs estimates based on further exploration of the connection charging statements.
This example offers more accuracy against the average costs in that they are based on up-to-date costs for 2024 however stakeholders are to note:
They do not include any reconfiguration costs. These are not considered typical and are specific to the local network configuration.
Total costs are based on single connection per application. Therefore, design fees have potential to reduce where connections are grouped. However, they do not include 4% margin applicable to non-contestable works for applications with higher total kVA.
They represent estimated costs in October 2024. These costs are updated annually.
Three Phase Connection up to 69kVA in typical footpath (pavement), in East Midlands:
Activity | Cost | Quantity |
---|---|---|
Assessment and Design Fees | £160 | 1 |
Three phase underground service (up to 69kVA) in a typical footpath including: Joint Supply and Installation Joint Hole - excavation Cut-Out Supply and Installation Road Closure Permits Other proportionally low-cost miscellaneous items e.g. alkathene tube, plastic marker tape, etc. | £866 - £1562 | 1 |
Installation of cable in a typical footpath | £108 - £175 per metre = £324 - £525 | 3 metres |
TOTAL | £1370 - £2247 + VAT |
We use essential cookies to make our website work and provide you with a good experience. Full details can be found in our cookie policy . We'd like to set additional cookies to understand how you use our website and remember your settings.