In order to connect to our network, we need to provide you with a connection offer which sets out the works to be undertaken, the cost of delivering those works and the terms and conditions to be applied. The types of connection offer available and the General Terms and Conditions are set out below.
If you are not ready to enter into a formal agreement for connection works, or you do not yet have full details of the specific connections required, you may opt for a budget estimate. This will provide you with an estimate of the likely cost of the connection before you make a formal application to us.
If you request a budget estimate, you will need to provide us with the following information:
A budget estimate will be an indication of the potential connection charge. However, it is important to note that this is a desktop exercise and will not involve a site visit, analysis of the wider network or any technical studies.
No, as it is an indication only there will be no ability to accept a budget estimate. If you are ready to proceed, you may contact us to provide you with a formal offer which can be accepted. You may need to provide more detailed information to enable us to complete a technical study.
A formal offer for connection will be provided where you have all the necessary information we require in order to make an assessment of the works required. The offer will contain specific terms for connection and reference the general terms for connection. Once accepted by you, it will become a binding contract between us.
We require information from you to enable us to make a reasonable assessment of the works required to facilitate the requested connections. This will include (but is not limited to):
*For embedded (IDNO) networks the point(s) of supply and associated capacities should be provided
A connection offer will provide a description of the non-contestable and contestable works to be carried out in order to provide you with your required connections and the associated charges for us to carry out those works. The connection offer will include a Letter of Acceptance. Signing this Letter of Acceptance will enter the customer into a binding contract for the works.
Connection offers are valid for 90 days after which they automatically expire.
In some instances, we may enable a single extension to the validity of the acceptance for a further 90 day period, provided there is no detrimental impact on other customers in the connections queue. To request an extension you must submit a request, in writing, no more than 10 days prior to the original connection offer validity expiry date. Upon receipt, we will confirm your revised expiry date or issue a letter outlining the reasons for refusal of the request.
Small Connection Works Offer
Small connection works are those provided for up to 4 domestic dwellings with only low voltage works required, a one-off commercial connection requiring service connection works only and up to 100A per phase or a service alteration to move the position of a meter.
Example small connection works offer letter
Dual Connection Offer
Larger connection schemes will receive a dual connection offer (sometimes known as a convertible connection offer) which provides two options. Option 1 is for NGED to undertake all of the connection works and Option 2 is for NGED to carry out the non-contestable works only, enabling you to appoint an Independent Connection Provider to complete the contestable elements.
Example HVLV Dual Offer letter
Example EHV Dual Offer letter
CiC POC Offer
In some instances you may not be ready to enter into a formal contract for connection works but feel a budget estimate will not provide the level of detail you require to consider the potential for development. We offer feasibility studies for which we will carry out a more detailed feasibility study to establish the viability of making a connection to our network. We will carry out preliminary network analysis and provide an indicative connection assessment outlining the engineering scheme for the connection.
The feasibility study will provide you with a more detailed assessment and engineering design solution for the site requirements. This will include consideration of any reinforcement works identified.
The feasibility study will not provide you with a Connection Offer which you can accept to enter into a contract for connection works.
Please email or write to us with your requirements here.
Feasibility studies are a chargeable service, as set out in Section 7 – Part B of the Connections Charging Statement.
If you are looking to connect Power Generating Modules, a Study & Offer quote enables you to assess the capacity options available without submitting multiple formal applications.
A Study & Offer request may be submitted for Power Generating Modules with a proposed export capacity of 5MVA and above.
Please complete the relevant application form and enclose the below supplementary Study & Offer request form:
Each application allows up to three different capacity options you may require.
We conduct a Feasibility Study for the approximate cost and works required to connect the generation to our network. This includes an indication of any reinforcement or diversionary
works that may be required. The start date for the Feasibility Study will be subject to the correct information being provided along with the Study & Offer application form.
Upon completion you have the choice to develop the Feasibility Study into a Connection Offer. If you accept one of the capacity options a Connection Offer will be prepared and sent out to comply with our Guaranteed Standards of Performance.
If you choose to accept one of the Feasibility Study options within 5 working days, your start date for the Feasibility Study will be used throughout the offer process. If the connection offer becomes interactive with other connection offers using the same part of the network, your application date will determine the position in the interactive queue.
There may be instances where we cannot provide the full required connection characteristics at all times without undertaking significant reinforcement works. To mitigate the costs or timescales associated with those works, we may offer a flexible connection solution to meet your needs, either on a temporary basis or as a more enduring solution.
The leaflet below sets out the flexible connection solutions currently offered by NGED.
We aim to provide a comprehensive design and cost for the connection works. However we recognise that, in some instances, changes need to be made and there may be occasions where we need to vary the Connection Charge or specific clauses within the Connection Offer.
Minor changes which are not substantial and do not fall outside of the “Allowable Changes” criteria will be dealt with using the variation process. However, where a change is deemed to not be allowable or is a substantial change, the variation process will not be appropriate.
We have provided a guidance document, available here, which sets out more information on Allowable Changes and the process for managing more substantial changes.
Where we require a variation, we will provide a variation letter which sets out the changes to be applied to the original Connection Offer, including any changes to the Connection Charge.
You do not have to accept the variation but, depending on the changes being applied, a failure to accept mandatory or required variations may prevent the connection works from proceeding further.
We have produced a guidance document to provide an indication of the more common circumstances where the Connection Offer may need to be varied, and a typical range of potential cost variation for larger HV and EHV connection requests. Please click here to view the guidance.
A signed Letter of Acceptance enters the customer, as specified within the offer, in to a binding contract with NGED. We recognise that there may be occasions where the contract needs to be transferred to a third party. To do this, we will require a Novation Agreement which enables all parties to agree the transfer of the contract.
Upon completion, the new customer is treated as though they have always been the customer and the original customer no longer has any rights or responsibilities under the contract.
A sample Novation Agreement is available below;
Connection Offers issued will include site specific conditions and arrangements. In addition, all connection offers will be subject to our General Terms & Conditions for connection. The general conditions should be read in conjunction with your connection offer and specific conditions.
We have two sets of General Terms & Conditions, one relating to Small Connection Works and one relating to all other connections.
Small connection works are those provided for up to 4 domestic dwellings with only low voltage works required, a one-off commercial connection requiring service connection works only and up to 100A per phase or a service alteration to move the position of a meter.
The following General Terms and Conditions apply for small connection works:
SSQ General Conditions V1 December 2017
SSQ General Terms for Connection V2 September 2022
SSQ General Terms for Connection V3 March 2024
The following General Terms and Conditions apply for connection works which do not fall into the Small Connection Works category*:
General-T-Cs-V1-Dec-2017
General-T-Cs-V2-March-2018
General-TCs-V3-June-2018
General-TCs-V4-August-2018
General-TCs-V5-March-2019
General-TCs-V6-June-2021
General-TCs-v7-Sept-2022
General-TCs-v8-April-2023
*Your connection offer will specify which version of the General Terms and Conditions is applicable at the time of issue.
The following General Terms and Conditions apply for diversionary works:
General Conditions for Diversions v2 Oct 2021
General TCs - Diversion Works V3 Sept 2022
Where the Customer wishes NGED to supply any meter cabinets, ducts and/or service tubing (less draw cords) and the cost of these items have already been included in the Offer, collection may be made by prior arrangement with the local NGED Construction Team at the locations within the below document.
When NGED receive two or more applications for a connection which make use of the same part network, or network assets, the applications become interactive. The resulting Connection Offers are termed Interactive Connection Offers.
Interactive Connection Offers form a queue based on their application date. When an Offer becomes interactive a Customer’s ability to accept their Connection Offer is then dependant on their position in the interactive queue and the outcome of the Offers ahead of them within the queue.
Details on NGED's process for Interactive Connection Offers can be found in our Interactive Process Guide.
Following industry consultations throughout 2019 and 2020, regarding Interactivity and Connection Queue Management, the Energy Networks Association published the Interactivity Process Guide. The purpose of the guide was to create an industry-wide agreed process that all network companies will use to manage interactivity.
NGED's policies and processes have been updated to comply with, and should be read in conjunction with, the ENA Interactivity Process Guide.
When customers apply to NGED for a connection, whether demand or generation, they are given a Connection Offer for the required capacity. There is a finite amount of capacity on any given area of network. Once that capacity is fully utilised network reinforcement may be required to create additional capacity. This reinforcement has both cost and time implications for new connection Customers looking to connect to NGED's network.
In assessing any new connection request, NGED need to take into account existing connected sites and customers that have accepted connection offers but have not yet connected. These “accepted but not yet connected” offers are generally termed simply Accepted Offers.
If there is limited capacity currently available Accepted Offers can have an impact on the cost and design of any subsequent Offers issued. This impact forms the “connections queue” – with Accepted Offers ahead effecting Accepted Offers “behind” in the queue.
Many of these Accepted Offers progress their connection to energisation in line with the agreed timescales. However, where a Accepted Offer is not progressing, this delay can adversely impact upon other Offers that are ready to progress but await completion of reinforcement works. This is not the most efficient way to allocate network capacity. Connections queue management is therefore achieved by ensuring Accepted Offers progress in line with their contractual Milestones.
NGED employs two forms of queue management, both centred around the application of Offer Milestones to ensure capacity is allocated fairly and connections progress in a timely manner. For Demand connections we utilise Milestones via the Allocation & Reservation of Capacity process, guidance for this process can be found by following this link to our Allocation and Reservation of Capacity Guidance.
For Generation connections we utilise Milestones via the generation Queue Management process. This process has now been updated in line with the recently published guidance from the ENA – the ENA Queue Management Guide. NGED's new guide can be found by following this link to our Queue Management guidance. This guidance has been updated to comply with, and should be read in conjunction with, the ENA Queue Management Guide.
We use essential cookies to make our website work and provide you with a good experience. Full details can be found in our cookie policy . We'd like to set additional cookies to understand how you use our website and remember your settings.