Connect and notify process

Guidance for Charge Point Operators on ‘Connect and Notify’ process for Existing Unmetered Supplies.

A "Connect and Notify" process for the installation of EV Charge Points (EVCPs) to existing unmetered supplies is now available. This self-serve process involves the Charge Point Operator (CPO) performing the required steps to determine if the existing connection is suitable for a charge point installation, following the steps set out below. 

It allows CPOs to perform the checks, do the installation and notify us in batches of installation - providing certain criteria are met. 

Preparation

Pre-approval surgery

Installation

Notification

Key information required from CPOs

Location of installation

Data requirement Source
Street Furniture Column Number Local Authority (LA) plans / On-site inspection
Grid Reference (Easting and Northing Grid References for Column) On-site location confirmation
Installation Address (Nearest Property number, Road/Street) On-site location confirmation
Town On-site location confirmation
Postcode On-site location confirmation

Existing supply details

Data requirement Source
Confirmation of Unmetered Connection On-site inspection / Local Authority
Unmetered MPAN - requested from NGED for EVCP installations, not existing LA MPAN Unmetered Supplies Operator (UMSO)
Cut-out fuse is 25 Amps On-site inspection
The service has a minimum cable size of 4mm2 CU On-site inspection
The supply is deemed safe On-site inspection
Service is not looped On-site inspection of column and adjacent columns

Proposed supply

Data requirement Source
Confirmation that charging equipment is single phase Manufacturers Specifications
Rating of Charging Equipment (kVA) Manufacturers Specifications
The proposed maximum load at the connection ≤5.75kVA Manufacturers Specifications (new load) and Local Authority (existing load)
Earthing Arrangement complies with Section 3.4 of NGED's ST SD5F Section 3.4 of SD5F and as proposed as approved as part of Technical Standards Agreement
Installation complies with the requirements of Section 3.1.1 of NGED's ST SD5F Data Portal 2
The supplying transformer has sufficient headroom National Grid Connected Data
Impedance of the connection satisfies the requirements of Table 1 in NGED's ST SD5F On-site measurement of connection impedance
Proposed installation complies with the BS EN 61000-3-2 and 61000-3-3 for harmonics and flicker Manufacturers Specifications