Connect and notify process

Guidance for Charge Point Operators on ‘Connect and Notify’ process for Existing Unmetered Supplies.

A "Connect and Notify" process for the installation of EV Charge Points (EVCPs) to existing unmetered supplies is now available. This self-serve process involves the Charge Point Operator (CPO) performing the required steps to determine if the existing connection is suitable for a charge point installation, following the steps set out below. 

It allows CPOs to perform the checks, do the installation and notify us in batches of installation - providing certain criteria are met. 

Preparation

Pre-approval surgery

Installation

Notification

Key information required from CPOs

Location of installation

Data requirementSource
Street Furniture Column NumberLocal Authority plans / On-site inspection
Grid Reference (Easting and Northing Grid References for Column)On-site location confirmation
Installation Address (Nearest Property number, Road/Street)On-site location confirmation
TownOn-site location confirmation
PostcodeOn-site location confirmation

Existing supply details

Data requirementSource
Confirmation of Unmetered ConnectionOn-site inspection / Local Authority
Unmetered MPAN - Last 13 digitsUnmetered Supplies Operator (UMSO)
Cut-out fuse is 25 AmpsOn-site inspection
The service has a minimum cable size of 4mm2 CUOn-site inspection
The supply is deemed safeOn-site inspection
Service is not loopedOn-site inspection of column and adjacent columns

Proposed supply

Data requirementSource
Confirmation that charging equipment is single phaseManufacturers Specifications
Rating of Charging Equipment (kVA)Manufacturers Specifications
The proposed maximum load at the connection ≤5.75kVAManufacturers Specifications (new load) and Local Authority (existing load)
The Earthing Arrangement complies with Section 3.4 of NGED's Standard Technique: SD5FSection 3.4 of SD5F and as proposed as approved as part of Technical Standards Agreement
The installation complies with the requirements of Section 3.1.1 of NGED's Standard Technique SD5FData Portal 2
The supplying transformer has sufficient headroomNational Grid Connected Data
The impedance of the connection satisfies the requirements of Table 1 in NGED's Standard Technique SD5FOn-site measurement of connection impedance
The proposed installation complies with the BS EN 61000-3-2 and 61000-3-3 for harmonics and flickerManufacturers Specifications