New Connections process

Customer guidance on NGED’s process for programmatic on street Electric Vehicle Charge Point (EVCP) connections.

An optimised process for new, programmatic EVCP connections is now available.

This process includes:

  • Self-serve pre-screening process to optimise site selection
  • NGED point of contact for each Local Authority to coordinate work across the business
  • Annual Connection Surgeries to review sites and phase work over the year, to synchronise quotations with customer’s implementation schedule

Pre-screening

There are three steps to pre-screen your sites – pre-screening will provide you with an initial indication of network readiness at each location. Sites that do not meet the criteria are likely to take longer to deliver, could be more expensive, or just may require more detailed network study to assess.

Connection surgery

The next step involves meeting a network planner to discuss the sites and agree the program of work for through the year.

Application Initiation

After the Connection Surgery, the customer needs to initiate applications in phases throughout the year.

Ongoing Engagement

Regular communication is encouraged as your program progresses to inform of any changes and prepare for year 2 of delivery.