Programmes of new connections – On-Street EV

Customer guidance on NGED’s process for programmes of new connections for on-street EV.

An optimised process and a set of tools are available to all customers, including Independent Connection Providers (ICPs). The process includes:

  • A self-serve pre-screening step to support site selection
  • A named NGED point of contact for each Local Authority to coordinate activity across NGED
  • Annual connection surgeries to review sites and phase work over the year, and align quotations with customers' implementation schedules

Pre-screening

Pre‑screening provides an initial indication of network readiness at each location. Sites that do not meet the criteria may take longer to deliver, may be more expensive, or may require a more detailed network study.

Connection surgery

The next step is a meeting with your NGED point of contact to review your sites and agree the programme of work for the year.

Application initiation

After the connection surgery, the customer needs to initiate applications in phases throughout the year.

Ongoing Engagement

Regular communication is encouraged as your programme progresses, to confirm any changes and prepare for Year 2 of delivery.